Our excellent association with MSEDCL & PWD Electrical Inspectorate enables us to provide efficient services in Legal Liasoning activities which comprises of submission of application, processing and obtaining load assurance sanction, up to completion of release order with transparency and highly appreciation from Liasoning Officials.
We are associated with different organizations especially Maharashtra State Electrical Distribution Company Limited and Public Welfare Department. We are also efficient in services like legal liasoning work which covers submission of application, processing of application and load assurance sanction. We are also work for completion of release order with high appreciation and transparency from Liasoning Officials.
What is Contract Demand and CD penalty?
Whenever you apply for a commercial electricity connection from a utility, you have to specify the maximum “demand“ (in kVA) that you need or Contract Demand (CD). During the month if you exceed your “Contract Demand” you have to pay a penalty (or extra price) for the same. That is the CD penalty that appears on your electricity bills.
How can CD penalty be avoided?
If your power factor is less than 1 you can improve your output kW per KVA supplied by improving the power factor or installing an Automatic Power Factor Controller (APFC Panel). This ensures that you are not wasting any kVA that is supplied to you by your utility.
The power factor is unity, but still, the CD penalty is levied by the utility, in such scenario, you may have to request your utility to increase the contract demand. Still confused? Talk to our experts [Speak to our Expert]
Another option for avoiding CD penalty is by shifting your peak load to a time of day when your load is less.